A project is often divided into smaller tasks. When each task is completed, we say that project is completed 100%. In that case we would like top monitor how task is completed while we work on the project. In this article, we will learn how you can calculate the project complete percentage in Excel
Generic Formula For Project Complete %
=COUNTIF(status range,“finished”)/COUNTA (tasks range)Status range : It is the range in which status of task is written.
Finished: Here “finished” word is used when a task of project is completed. You can use any word you want.
Tasks range : The range in which tasks are listed
Let’s see an example to make things clear. Example: Calculate Project Complete Percentage in Excel
Here I have a list of tasks in range A3:A14. Their status is written in range B3:B14. We need to calculate percent complete in excel.
Apply above generic percent complete formula
=COUNTIF(B3:B14,"finished")/COUNTA(A3:A14)It will return a fraction number. Change the formate to percentage using excel shortcut CTRL+SHIFT+5. And it’s done.
How it works?
Well, it is a simple excel formula. We count the number of completed tasks in excel using COUNTIF(B13:B14, “finished”).
Than we divided the number of completed tasks from total number of tasks using /COUNTA(A3:A14). Finally we formated that cell as percentage. And that is it. We have calculated percentage of project completion in excel using a simple formula. So yeah guys, this how you calculate total percentage in excel. Let me know if you have any doubts regarding this excel topic or any other. The comments section is all yours.
Related Articles
Calculate Percentage of Total in Excel
Calculate Percentage Discount
Increase by percentage
Calculate Profit margin percentage
Popular Articles:
The VLOOKUP Function in Excel
COUNTIF in Excel 2016
How to Use SUMIF Function in Excel
Tag » How To Find Percent Complete
-
Percent Complete - Project Plan 365
-
Completion Percentage Calculator
-
Percent Complete Display And Calculations - IBM
-
Percent (%) Work Complete Fields - Microsoft Support
-
How To Calculate A Project Complete Percentage (Plus Uses)
-
How To Track Percent Complete
-
How To Calculate Percent Complete In Project Management
-
Understanding Project's Percent Complete Vs. Percent Work Complete
-
Easy Method Of Calculating The Percentage Of Task Complete - YouTube
-
How To Calculate Percent Complete For A Project - YouTube
-
Excel Formula: Project Complete Percentage | Exceljet
-
Percent Complete Calculations
-
Percent Complete (Oracle Projects Help)
-
The Percentage Of Completion Method Explained - Levelset